Phase I
Provides space for 734 students.
Start of construction: mid-May, 2006.
Includes the demolition of Wahr Hall, Administrative Annex, and Greenhouse.
Expected completion of construction: mid-August, 2007. The rendering above
is the proposed finished product and shows the corner of Grant Street and
Pratt Drive.
Phase II
Provides space for approximately 1,094 students.
Expected start of construction: May, 2007.
Includes the demolition of Langham, Turnbull, Stewart, Mack and Gordon Hall.
Expected completion of construction mid-August, 2008.
Phase III
Planning is in progress.
Phase IV
Planning is in progress.
|
|
|